Santos - Raslie, Pickanjinnie & Coxon Creek Holding Dam Liners
Projects ~ Liners
Principal: SANTOS
Head Contractor:
Location:
Date: 1304473065_Raslie,-Pickanjinnie.jpg
Project Scope:
Three ponds requiring the installation of HDPE liners with a total area of approximately 150,000m2. Materials were contracted by Santos and supplied by Fabtech, the installation was contracted by Bardrill to Fabtech.
The ponds are of composite liner design using 1.5mm HDPE liner material. In addition to on site QC protocols third party NATA lab testing of destructive weld samples were also undertaken.