SA Water - Aldinga Waste Water Treatment Plant Southern Urban Water Re-Use Project

Projects ~ Covers

Principal: SA Water
Head Contractor: Leed Engineering
Location: Aldinga, SA
Date: July 2010

Project Scope:

Supply and construction of liner and floating cover systems inclusive of associated civil works for the storages being part of the State Government Water Eefficiency Improvement Programme. The new waste water treatment plant was constructed requiring a lined and covered effluent feed pond and two lined and covered recycled water storage ponds.

Additional Information:

The liner and cover were both secured to a concrete ring beam with stainless steel battening bar. The ring beam was specifically designed to stand above the crest pavement level to provide a kerb to reduce debris blowing onto the cover to reduce cover maintenance requirements.