Supply and installation of a 170,000m2 area landfill cap
to the Portsmith landfill requiring 680,000m2 of
materials. The cap comprised a four layer sealing and
drainage design including a thin layer X800 series GCL
liner over the CCL cap. This was covered with 1mm
textured LLDPE, a geocomposite drain layer and a filer
[ + read more ]
Supply and installation of Fabtech designed and
certified high volume low aspect ratio holding tanks
configured both individually and combined in a tank farm
configuration. The selected holding capacities were 2.5
and 3.4 ML’s. The contract currently comprises 27
units.
[ + read more ]
Supply and installation of 1.5mm HDPE liner with a
partial geotextile cushion layer to two ponds totaling
approximately 120,000m2 of surface area in two discrete
mobilisations. The client required a high installation
rate necessitating allocation of a large installation
team accommodated in the clients adjacent camp
[ + read more ]
Installation of lining systems to 500,000m2 of surface
configured as four discrete ponds with connecting
spillways, HDPE plate sumps, and HDPE plate mounting
systems for inlet and outlet pipework. This required in
excess of 150km of fusion seam welding to strict QC
requirements. The lining system comprised a geotextile
[ + read more ]
Supply and installation of geotextile cushion layer and
a 2mm HDPE primary liner for the feed water lagoon
system and effluent pond at the clients’ water
treatment plant. The surface area of the system was
approximately 170,000m2. The installation included
spillways, causeways and other structures with the
[ + read more ]
Prior to contract award Fabtech provided specification
and design advice to AGL. Fabtech were contracted by
Ostwald Bros who were the head contractor for this
remote area holding pond. The project was for supply and
installation of a geotextile cushion layer under an HDPE
liner system. The surface area lined was approximately
[ + read more ]
Three dams requiring the installation of HDPE liners
with a total area of approximately 150,000m2. Materials
were contracted by Santos and supplied by Fabtech, the
installation was contracted by Bardrill to Fabtech.
The dams are of composite liner design using 1.5mm
[ + read more ]
Design, supply, construct and install liner and floating cover system for Mt Pleasant Water Storage Pond. The design comprises Enviroliner lining systems with Reinforced Polypropylene defined sump cover systems.
Design and construction of a 10ML potable water storage cover using a specialist white alloyed polyethylene membrane in 1mm grade.
Design and Construction PP lining and RPP cover systems for a 180ML potable water storage basin including civil works, pipe systems and security.
Water storage Lagoons approximately 60,000m2 of HDPE supplied and installed.
Installation of 1.5 mm HDPE geomembrane liner with leak detection systems to five waste water storage lagoons totalling 112,000 m2
Supply and Installation of 3 process water ponds including leak detection systems in HDPE.
Supply and Installation of a 1.5mm HDPE and AYY geomembrane liner and stockpile Pad 14,500m2. 2x Storage Dams – 33,800m2 and 6.500m2.
Supply and Installation of a 1.0-mm thick HDPE geomembrane liner for the dam located at Jacinth-Ambrosia Mine totalling 3,000m2.
Supply and Install HDPE for wall raise to an operational evaporation pond.
Installation of 500,000m2 of 2mm HDPE and Geotextile for a cellular evaporation pond system.
Supply and Installation of a 1.5-mm thick HDPE geomembrane liner in the East and West Storm Water Dams at BHP-Billiton Olympic Dam.
Design, supply and install 3x storage lagoons for Beverley Mines. To assure environmental performance the process lagoons have a double linier system with leak detection systems.
Installation of a small leach pad using HDPE geomembrane for this remote site mine.
Design and Construct Project for removal of existing PP cover, design of new HDPE cover, gas collection and rain water disposal system for a HRAL. Installation was performed over the full but decommissioned lagoon.
Design, supply and installation of three lined and covered WWT storage lagoons with Polypropylene liners and RPP defined sump floating covers. Approximate value $900k.
Supply and Installation of a landfill cap in LLDPE, approx 90,000m2, with cushion geotextile and multiple gas pipe penetration sealing.
Design, Supply, Installation and Testing of 2 x 4 ML and 2 x 7 ML membrane lined and covered earthen water storages including leak detection systems processing waste water. The liner systems were constructed in Polypropylene and the pre-fabricated covers in reinforced Polypropylene.
Design and Construction of an LLDPE cover for a 200ML water storage.
Design and Construction of HDPE liner and RPP gas extraction cover for a 4ML effluent storage basin and HDPE liner and RPP gas cover and pipework systems for two 21ML anaerobic reactors.
Design and Construction PP lining and RPP cover systems for a 50ML Potable water storage basin including civil works and pipe systems.
Design, Supply and Installation of biogas collection cover for the Werribee Farm Treatment Works. The cover is a three layered collection cover which incorporates a bottom layer of HDPE to act as a scum control device, a layer of polyethylene foam providing odour control and an upper layer of 45 mil reinforced polypropylene. This project totals approximately 90,000 square metres of cover material. The size of the project dictated a complex installation design incorporating purpose designed installation pontoons. Fabtech subcontracted and project managed all the pipework, electricals, flaring and concrete ring beam. This project is the largest constructed in the world
Design, Supply and Installation of biogas collection cover for Goulburn Valley Water’s Shepparton High Rate Anaerobic Lagoon (HRAL). The biogas collection is at present to be flared off with capacity for power generation at a later date. The total area covered was 54,000 square metres
Design, Supply and Installation of liner and anaerobic floating cover for Ingham’s Murarrie treatment plant
50,000m2 Design, Supply and Install of polypropylene liner and reinforced polypropylene cover for potable water supply for East Gippsland Water including associated concrete structures.
Supply and install effluent gas cover. This incorporates a 2mm HDPE cover installed over an effluent lagoon, and bio-gas flare. A co-generation system is incorporated to allow use of gas produced
Design, Supply and installation of 25,000m2 PP liner and RPP cover for potable water supply including civil works and pipe work.
Construction, lining and covering of 6.5ML potable water storage dam, 8,000m2 of reinforced polypropylene
Supply and installation of 1.5mm HDPE liners and 1mm EL6000 gas collection cover
Reinforced polypropylene baffle curtain to waste water treatment plant
Design, supply and install two reinforced polypropylene baffle curtains
Design, supply and installation of liners and floating covers for Effluent Anaerobic Lagoons
Design, supply and installation of liners and floating covers for effluent anaerobic lagoons (5) for winery applications
Design, supply and installation of liner and floating cover and bio gas collection system for effluent anaerobic lagoon
Design, supply and install polypropylene bio gas collection floating cover for co-generation
Supply and install polypropylene baffle curtain for STEDS Scheme
Supply and install polypropylene baffle curtains to wastewater lagoons
Design, supply and install polypropylene effluent curtain
Supply and Installation of HDPE geomembrane lining systems for a waste water storage lagoon. Approximately 21,000m2.
Supply and Installation of a 1.5-mm thick HDPE geomembrane liner in the storages included in the Wimmera Mallee Pipeline Project - 45,498m2.
Supply and Install HDPE lining systems to 2x abattoir effluent lagoons. Approximately 10,000m2.
Supply and Install HDPE liners to 4x waste water storage lagoons. The project included multipule concrete structures and penetrations requiring complex sealing systems. Approximately 23,000m2 of material.
Supply and installation of 1.5mm HDPE geomembrane liner for a waste water dam located at Lyndoch, Approx. 12,000m2 of 1.5mm HDPE material.
Supply and installation of 1.5mm thick HDPE Geomembrane Liner approx. 24,000m2 for a Stormwater Lagoon.
Supply and installation of geomembrane liners in 3 ponds for Como Glasshouse Stage 2 Project. Approx. 60,000m2 of 1.5mm HDPE lining materials
Lining of WWTP lagoons for Ceduna Council using HDPE including design and construction of an under-liner gas release system.
Supply and installation of 1.5mm HDPE to a waste water storage lagoon of 25,000 m2.
Supply and install HDPE liner to effluent sump
Supply and install HDPE liner for retention of contaminated waste
Supply and Install 330,000m2 of 1.5mm HDPE for heap leach pads and storage ponds.
HDPE liner to sewage lagoon
Tailings dam liner including double liner leak detection system comprising 240,000m2 of surface.
Supply and Installation of HDPE lining system with geotextile cushion layer to an earthern storage lagoon. Approximately 100,000m2.
Supply and installation of HDPE lining systems with geotextile cushion layer to a brine storage and a chemical waste water storage. Approximately 130,000m2.
Supply and Installation of 240,000m2 of HDPE membrane to heap leach pads, W drains, process ponds and storm water ponds for the White Dam Gold mine in Northeast SA.
Supply and Installation of HDPE primary and secondary lining systems and leak detection system.
Supply and Installation of 1.5mm HDPE lining system to 3x waste water storage lagoons. Approximately 100,000m2.
Supply and Install 180,000m2 of 2.0mm HDPE with geotextile underlay for a waste water treatment lagoon system.
Supply and Installation of 1.5mm HDPE lining system to a wastewater storage lagoon. Approximately 50,000m2 of material.
Build and lining of a waste water storage lagoon. The project included construction of the dam and lining with cushion layer geofabric and 2.0mm HDPR liner. Approximately 50,000m2 of liner surface.
Design, supply and installation of double lined process water ponds including leak detection, monitoring and automatic pumping system with the entire system being fabricated and installed by Fabtech. 2.00mm HDPE primary liners, M5 flow net, 1.00mm HDPE secondary liners, precast concrete wells and automatic pump systems.
Design and Construction of 5 storage lagoons in HDPE with 2.00mm HDPE primary liners and 1.5mm secondary membranes with automatic leak detection systems for Uranium One’s Honeymoon ISL Operations.
Supply and install of HDPE liner and geotextile to Origin’s Condabri Lagoon. The QA regime included third party destruction weld seam testing. The dam was 55,000 m2 in area with textured membrane on the batters and smooth material on the floor.
Supply and Installation of 1.5mm smooth HDPE for waste water storage dams total 20,000m2.
Supply and Installation of a 1.5-mm thick HDPE geomembrane liner totalling 11,000m2.
8,100m2 1.5mm HDPE
Supply and installation of a 1.5-mm HDPE Geo-membrane totalling 22,000m2.
60,000m2 of 1.5mm HDPE for reclaimed water storage lagoon.
Supply and installation of 7,200m2 1.5mm HDPE liner to STEDS scheme
Design, supply and installation of 1.5mm HDPE liners for effluent lagoons for processing plant
Supply and install 1.0mm HDPE liner to dam at Santa Teresa Sewerage upgrade
Supply and install 1.5mm HDPE liner to two dams for Jilkminggan Sewerage upgrade
Supply and install 2.0mm HDPE liner for Bolivar treatment Plant for effluent containment
Supply and install wastewater/effluent tank liners to treatment plant
Supply and install wastewater/effluent tank liners to treatment plant
Supply and install HDPE liner for CCA treatment sump area
Supply and install geotextile and 1.5mm HDPE liner for solid containment
Supply and install PVC liner for effluent containment
Supply and install HDPE methane gas prevention liners
Supply and install HDPE liners for Reed Bed Effluent Treatment
Supply and install 1.0mm HDPE liners for bio-remediation pads
Supply and install polypropylene liner to effluent system
Supply and install PVC liners to holding lagoons
Supply and install HDPE liner for effluent containment
Lining of a wet weather pond and catchment pond HDPE 2mm 16,600sqm
Supply and installation of a 1.5-mm thick HDPE geomembrane liner also including drainage flow-net leakage detection for the water storage dams
Supply and installation of a 1.0-mm Smooth HDPE Geomembrane totally 4,025m2
Supply and installation of Geonet, Geomembrane and Geotextile for a landfill application in Dublin, including rigrous QA specifications. Approx. 60,000m2 of materials.
Latrobe City Hyland Highway Landfill for the supply and installation of HDPE geomembrane including gusset to leachate pipe.
Supply and install Geotextile and GCL to landfill
Supply and installation of 2mm smooth and textured HDPE, two layers of GCL and geotextile to landfill
Supply and install 1.5mm HDPE, GCL and geotextile to landfill
Supply and installation of 50,000m2 of 1.5mm HDPE, GCL and two grades of geotextile for leachate collection at Wyong Shire Landfill